• April 2022
    • The small blue house behind KHS was removed to prepare the remaining area for tree removal.
  • May 2022
    • Trees were removed and the lots behind KHS began to be cleared.
  • June 2022
    • Demolition in the current student parking area began to move tennis courts to this area.
    • Area behind KHS began being prepared for temporary student parking.
  • March 2022
    • Seating in the north end zone was taken down and removed.
  • April 2022
    • Concession stands on the home and visitor sides were torn down and removed
    • Mens and womens restrooms on home and visitor sides were torn down and removed.
  • June 2022
    • Although not part of the bond project, turf on the field was removed and the field was prepped for new turf to be installed.
  • July 2022
    • Concrete was poured for curbs and to set fence posts.
    • Plumbing for new restrooms and concession stand was completed to prepare for foundations to be poured.
    • Added emblems (repurposed from removal from the scoreboard for the sound system installation) to the front gate. KHS Ag Mechanics department welded the emblems to create the entry.