


- April 2022
- The small blue house behind KHS was removed to prepare the remaining area for tree removal.
- May 2022
- Trees were removed and the lots behind KHS began to be cleared.
- June 2022
- Demolition in the current student parking area began to move tennis courts to this area.
- Area behind KHS began being prepared for temporary student parking.
- August 2022
- Soil was excavated and prepped for construction of the tennis courts
- September 2022
- Tennis courts were framed and concrete poured and leveled.
- October 2022
- Surface preparation for track construction and soccer field turf preparation.
DCIM\100MEDIA\DJI_0130.JPG DCIM\100MEDIA\DJI_0131.JPG



- March 2022
- Seating in the north end zone was taken down and removed.
- April 2022
- Concession stands on the home and visitor sides were torn down and removed
- Mens and womens restrooms on home and visitor sides were torn down and removed.
- June 2022
- Although not part of the bond project, turf on the field was removed and the field was prepped for new turf to be installed.
- July 2022
- Concrete was poured for curbs and to set fence posts.
- Plumbing for new restrooms and concession stand was completed to prepare for foundations to be poured.
- Added emblems (repurposed from removal from the scoreboard for the sound system installation) to the front gate. KHS Ag Mechanics department welded the emblems to create the entry.
- August 2022
- Door frames and walls for restrooms began to be constructed.
- A road at the south end of the of the stadium was constructed to allow bus access to both the home and visitor side of the stadium.
- Roofing was installed on the restroom facilities and the concession stand construction began.
- Turf installation was completed.
- Front gate and ticket area was repainted and fencing was replaced.