• April 2022
    • The small blue house behind KHS was removed to prepare the remaining area for tree removal.
  • May 2022
    • Trees were removed and the lots behind KHS began to be cleared.
  • June 2022
    • Demolition in the current student parking area began to move tennis courts to this area.
    • Area behind KHS began being prepared for temporary student parking.
  • August 2022
    • Soil was excavated and prepped for construction of the tennis courts
  • September 2022
    • Tennis courts were framed and concrete poured and leveled.
  • October 2022
    • Surface preparation for track construction and soccer field turf preparation.
  • March 2022
    • Seating in the north end zone was taken down and removed.
  • April 2022
    • Concession stands on the home and visitor sides were torn down and removed
    • Mens and womens restrooms on home and visitor sides were torn down and removed.
  • June 2022
    • Although not part of the bond project, turf on the field was removed and the field was prepped for new turf to be installed.
  • July 2022
    • Concrete was poured for curbs and to set fence posts.
    • Plumbing for new restrooms and concession stand was completed to prepare for foundations to be poured.
    • Added emblems (repurposed from removal from the scoreboard for the sound system installation) to the front gate. KHS Ag Mechanics department welded the emblems to create the entry.
  • August 2022
    • Door frames and walls for restrooms began to be constructed.
    • A road at the south end of the of the stadium was constructed to allow bus access to both the home and visitor side of the stadium.
    • Roofing was installed on the restroom facilities and the concession stand construction began.
    • Turf installation was completed.
    • Front gate and ticket area was repainted and fencing was replaced.